Key Points
- Robertson Construction Central East has been appointed to build an £8.75 million SP Energy Networks depot in Currie.
- Construction is scheduled to begin in December 2026, with completion expected in summer 2028.
- The project will replace outdated facilities beside the Currie substation serving Edinburgh and the Lothians.
- The 827-square-metre building will include offices, workshops and a reconfigured operational yard.
- Photovoltaic panels, air-source heat pumps, heat-recovery ventilation and rainwater harvesting are planned.
Currie (Edinburgh Daily News) November 26, 2026 – Robertson Construction Central East has been appointed to deliver a new £8.75 million operational energy depot for SP Energy Networks in Currie, near Edinburgh. Work is scheduled to start in December 2026 and is expected to finish by summer 2028. The facility will provide a modern base for teams maintaining the electricity network across Edinburgh, the Lothians and wider central and southern Scotland. The development will be delivered in phases so existing operations can continue during construction.
What will the new Currie energy depot include?
As reported by The Edinburgh Reporter, the replacement facility will be built beside the Currie substation, which acts as a transmission hub for Edinburgh and the Lothians. The project will replace outdated buildings with an 827-square-metre, two-storey structure combining office accommodation and workshops for SP Energy Networks staff.
The wider redevelopment will cover approximately 3,500 square metres. It will include a reconfigured operational yard, demolition of the current buildings, hard landscaping, electric vehicle charging points and accessible parking spaces.
How will the project reduce carbon emissions?
The design by Threesixty Architecture is intended to reduce operational carbon emissions by 82% compared with standard equivalent buildings. Planned measures include photovoltaic panels, air-source heat pumps, heat-recovery ventilation and a rainwater harvesting system for internal use.
The building will use a hybrid structure combining a steel portal frame with cross-laminated timber floor slabs. Its external design will include black standing-seam metal cladding and copper-toned detailing, while timber finishes are planned for open-plan office areas to support the use of natural daylight.
What have SP Energy Networks and Robertson Construction said?
Stephen Kelly, Transmission Operations Director at SP Energy Networks, said the investment would provide secure, sustainable and fit-for-purpose facilities for teams responsible for maintaining and strengthening the electricity network. He added that the new depot would create a more efficient and flexible workplace for future operations.
David Cairns, Regional Managing Director for Robertson Construction Central East, said the company was preparing to modernise the Currie site and would apply its experience of working in live operational environments. He said careful planning, collaboration and safety would be required to keep operations uninterrupted.
What is the background to the Currie depot development?
The project forms part of SP Energy Networks’ investment in facilities supporting electricity network operations. The existing buildings beside the Currie substation are being replaced because they no longer provide the modern operational accommodation required by network teams. Robertson Construction Central East was appointed through its regional construction business, according to Robertson Construction’s announcement. The development has been planned in phases to allow current activities to continue while the site is rebuilt. Completion is expected in summer 2028.
How could the development affect the contractor and local audience?
The appointment gives Robertson Construction Central East responsibility for delivering a major infrastructure-support facility in Currie, with work expected to continue through to 2028. For local residents and businesses, the phased approach is intended to limit disruption to the operational site while construction takes place. The completed depot should provide SP Energy Networks teams with improved workshop, office and yard facilities for maintaining the regional electricity network. The project may also create activity for construction and specialist suppliers involved in building services, landscaping and low-carbon technologies.